Rio Tinto signed two Australia’s renewable power contracts to decarbonise the Gladstone production assets

Telah Terbit: Feb 23, 2024 01:18 (GMT+8)
Sumber: SMM
In an effort to decarbonize its operations in Gladstone and meet its emission reduction targets, Rio Tinto has announced two major renewable power contracts. These renewable projects are a solar farm with a capacity of 1.1GW and a wind energy project of 1.4GW. Rio Tinto aims to reduce its carbon emissions by half by 2030 and achieve net-zero emissions by 2050. With the two projects, Rio Tinto is set to become Australia's largest renewable energy buyer and make a significant impact on regional economic and sustainable environmental development. The company's global decarbonization investment from 2022 to 2030 is projected to be between $5 billion and $6 billion, focusing on renewable energy, aluminum operations, and other decarbonization strategies.

In 2022, Rio Tinto announced its search for proposals to develop large-scale wind and solar power in central and southern Queensland. The initiative aimed to power its Gladstone production assets, achieve emission reduction targets, and further encourage the development of renewable energy. Gladstone hosts three facilities: the Boyne Island aluminium smelter with 584kmt capacity, the Yarwun alumina refinery with 3.4mt capacity, and the QAL alumina refinery with 3.95mt capacity. Currently, Gladstone's energy supply comes from Gladstone coal-fired power station which Rio Tinto owns 42% interest and a gas turbine co-generation plant owned by the Yarwun alumina refinery. The capacities of these two power plants are 1680 MW and 160 MW respectively.


As indicated in Rio Tinto’s 2023 annual report, two alumina refineries in Gladstone generate more than half of Australia's scope 1 carbon emissions and have therefore been the focus of efforts to be decarbonised. In March 2023, the Australian government enacted new legislation requiring large industrial carbon emitters to purchase carbon credits to offset their scope 1 emissions, as well as a requirement to reduce their baseline. Market challenges, changes in capital requirements and the increased cost of carbon emissions as a result of the new legislation, these factors triggered two refineries in Queensland impairments of $US700 million ($A1.1 billion) in 2023. As a result, Rio Tinto will be more proactive in accelerating the process of seeking renewable energy alternatives.


As the largest energy consumer in Queensland, Rio Tinto set ambitious goals to halve its carbon emissions by 2030 and reach net-zero emissions by 2050. The normal operation of Gladstone's production business requires 1140MW, equivalent to at least 4000MW of high-quality wind or solar power.


By the beginning of 2024, significant progress had been made towards these goals.


On January 24th, Rio Tinto announced the purchase of all electricity from the 1.1GW Upper Calliope Solar Farm for 25 years, powering its Gladstone operations. Operated by European Energy, the solar farm is located about 50 km southwest of Gladstone and is awaiting development and grid connection approvals. Once approved and developed, Upper Calliope has the potential to reduce Rio Tinto's operational carbon emissions by 1.8 million tons annually and is expected to start between 2025 and 2026, covering approximately 5% of Queensland's current electricity demand.


On February 21st, Rio Tinto declared it had signed Australia's largest renewable energy purchasing agreement to date with Windlab, for the Gladstone production operations. Under the agreement, Rio Tinto will buy 80% of the electricity from Windlab's 1.4GW Bungaban wind energy project for 25 years. Located about 40 km from Wandoan town and 290 km southwest of Gladstone, the wind project is in the early stages of development and awaiting approvals for development and grid integration. Once approved, construction of the Bungaban project is scheduled to begin at the end of 2025 and become operational by 2029, reducing Queensland's carbon emissions by approximately 4 million tons annually.


The combined capacity of the two projects mentioned above is 2.22 GW, which accounts for more than half of the high-quality renewable energy capacity estimated for Rio Tinto’s Gladstone operations. We assume that the goal of halving carbon emissions by 2030 will be achieved, provided the projects proceed as planned.


With the completion of these two renewable partnership projects, Rio Tinto will become Australia's largest renewable energy buyer. Rio Tinto’s global decarbonization investments budget from 2022 to 2030 is valued at $5 billion to $6 billion (A$7.6 billion to A$9.1 billion). The pathway to reduce carbon footprint is organised into six global decarbonisation programs focused on renewables, Pacific aluminium operations, aluminium anodes including ELYSISTM technology, alumina processing decarbonisation, minerals processing decarbonisation and diesel alternatives. Rio Tinto will continue to look for partnerships with renewable energy providers to support sustainability commitments, while also driving the transition to clean energy. These projects highlight Rio Tinto's positive progress towards a greener future, making a significant contribution to the regional economy and sustainable environmental development.

Pernyataan Sumber Data: Kecuali informasi yang tersedia untuk publik, semua data lainnya diproses oleh SMM berdasarkan informasi publik, komunikasi pasar, dan mengandalkan model database internal SMM. Hanya untuk referensi dan tidak menjadi rekomendasi pengambilan keputusan.

Untuk pertanyaan atau informasi lebih lanjut, silakan hubungi: lemonzhao@smm.cn
Untuk informasi lebih lanjut tentang cara mengakses laporan penelitian kami, hubungi:service.en@smm.cn
Berita Terkait
Penawaran Premium CIF MJP Q4 ‘26 yang Direvisi oleh RTA sebesar US$280/mt
25 Sep 2026 09:33 (GMT+8)
Penawaran Premium CIF MJP Q4 ‘26 yang Direvisi oleh RTA sebesar US$280/mt
Baca Selengkapnya
Penawaran Premium CIF MJP Q4 ‘26 yang Direvisi oleh RTA sebesar US$280/mt
Penawaran Premium CIF MJP Q4 ‘26 yang Direvisi oleh RTA sebesar US$280/mt
Tawaran Premium CIF MJP Q4 '26 yang Direvisi oleh RTA sebesar US$280/mt (turun dari US$310/mt). Berlaku hingga 28 Sep 2026
25 Sep 2026 09:33 (GMT+8)
Pabrik Penggilingan Aluminium Canggih Henan Yirui Mulai Berproduksi, Menargetkan Pertumbuhan Pasar Kelas Atas
24 Sep 2026 20:58 (GMT+8)
Pabrik Penggilingan Aluminium Canggih Henan Yirui Mulai Berproduksi, Menargetkan Pertumbuhan Pasar Kelas Atas
Baca Selengkapnya
Pabrik Penggilingan Aluminium Canggih Henan Yirui Mulai Berproduksi, Menargetkan Pertumbuhan Pasar Kelas Atas
Pabrik Penggilingan Aluminium Canggih Henan Yirui Mulai Berproduksi, Menargetkan Pertumbuhan Pasar Kelas Atas
Pada 20 September, pabrik penggilingan kasar pelat tebal dari proyek manufaktur cerdas bahan baru berbasis aluminium berkapasitas 720.000 ton per tahun milik Henan Yirui New Materials Technology Co., Ltd. resmi mulai beroperasi. Dengan total investasi RMB 1,5 miliar, proyek ini memanfaatkan lahan pabrik yang ada untuk membangun jalur pengerolan panas kontinu "1+4" yang canggih secara internasional, didukung oleh peralatan pemrosesan aluminium terdepan di industri seperti tungku pemanas ulang tipe dorong. Proyek ini juga telah membangun sistem IoT industri yang mampu memantau secara real-time dan mengatur secara dinamis parameter produksi inti seperti gaya pengerolan dan suhu, yang secara efektif menjamin kualitas stabil produk aluminium kelas atas dan terus meningkatkan pangsa pasar produk bernilai tambah tinggi.
24 Sep 2026 20:58 (GMT+8)
Guinea Perluas Kerja Sama Pertambangan dengan Glencore, Targetkan Peningkatan Pendapatan dan Industrialisasi
24 Sep 2026 20:58 (GMT+8)
Guinea Perluas Kerja Sama Pertambangan dengan Glencore, Targetkan Peningkatan Pendapatan dan Industrialisasi
Baca Selengkapnya
Guinea Perluas Kerja Sama Pertambangan dengan Glencore, Targetkan Peningkatan Pendapatan dan Industrialisasi
Guinea Perluas Kerja Sama Pertambangan dengan Glencore, Targetkan Peningkatan Pendapatan dan Industrialisasi
Guinea berencana memperluas kerja samanya dengan Glencore ke bidang pemurnian alumina, energi, emas, dan logam dasar, dengan tujuan meningkatkan pendapatan pertambangan, mendorong pemrosesan lokal dan industrialisasi sumber daya mineral, serta memperkuat kerja sama dengan pasar dan perusahaan pertambangan internasional di Tiongkok, Timur Tengah, dan kawasan lainnya.
24 Sep 2026 20:58 (GMT+8)