The Kakula copper project is ahead of schedule and is expected to be put into production in the third quarter of 2021.

Telah Terbit: Jul 7, 2020 14:29

SMM7: Canadian mining company Ivanhoe said on Monday that the underground development of its Kakula copper mine has exceeded expectations and has now completed 5.1km ahead of schedule, totaling more than 17km. The Kakula copper mine is expected to be put into production in the third quarter of 2021.

In June, the mining team completed an underground development of 1729 meters, 575m ahead of schedule for the month.

Ivanhoe also said that Kakula's 2000-ton ore conveyor system began operation in June, which will further increase the speed of underground development of the mine.

Underground development in the next few months will soon transition to high-grade mining areas.

The project is the first mine in a number of planned Kamoa-Kakula projects in the Democratic Republic of the Congo.

The Kamoa-Kakula copper project is a joint venture between Ivanhoe Mining (39.6%), Zijin Mining Group (39.6%), Crystal River Global Limited (0.8%) and the Government of the Democratic Republic of the Congo (20%).

The latest resource estimate for the large project, which was delivered in February, shows that it holds 1.4 billion tonnes of copper with a grade of 2.74 per cent (83.7 billion pounds) and another 339 million tonnes of inferred ore with a grade of 1.68 per cent and a copper content of 12.5 billion pounds (1 per cent).

"Click to participate in the second China (Yingtan) Copper Industry Summit Forum and the 15th China International Copper Industry chain Summit"

Scan the code to sign up for the summit or apply to join the SMM industry exchange group:

Pernyataan Sumber Data: Kecuali informasi yang tersedia untuk publik, semua data lainnya diproses oleh SMM berdasarkan informasi publik, komunikasi pasar, dan mengandalkan model database internal SMM. Hanya untuk referensi dan tidak menjadi rekomendasi pengambilan keputusan.

Untuk pertanyaan atau informasi lebih lanjut, silakan hubungi: lemonzhao@smm.cn
Untuk informasi lebih lanjut tentang cara mengakses laporan penelitian kami, hubungi:service.en@smm.cn
Berita Terkait
Foshan Huahong Pipa dan Tabung Tembaga, Produsen Terkemuka Guangdong, Mengumumkan Penutupan
11 jam yang lalu
Foshan Huahong Pipa dan Tabung Tembaga, Produsen Terkemuka Guangdong, Mengumumkan Penutupan
Baca Selengkapnya
Foshan Huahong Pipa dan Tabung Tembaga, Produsen Terkemuka Guangdong, Mengumumkan Penutupan
Foshan Huahong Pipa dan Tabung Tembaga, Produsen Terkemuka Guangdong, Mengumumkan Penutupan
Pada tanggal 21 Agustus, Foshan Huahong Copper Pipe & Tube Co., Ltd., yang berlokasi di Kota Shishan, Distrik Nanhai, Kota Foshan, mengumumkan penghentian operasinya. Perusahaan ini didirikan pada tahun 2004 dengan modal terdaftar sebesar 150 juta RMB, dan pernah menjadi perusahaan terkemuka di industri pipa dan tabung tembaga pendingin Foshan. Perusahaan ini juga masuk dalam 500 besar perusahaan manufaktur di Provinsi Guangdong dan diakui sebagai perusahaan teknologi tinggi tingkat provinsi.
11 jam yang lalu
Kailida menantikan pertemuan dengan Anda di Konferensi Tahunan Logam Non-Ferrous China Selatan SMM (ke-3) 2026.
12 jam yang lalu
Kailida menantikan pertemuan dengan Anda di Konferensi Tahunan Logam Non-Ferrous China Selatan SMM (ke-3) 2026.
Baca Selengkapnya
Kailida menantikan pertemuan dengan Anda di Konferensi Tahunan Logam Non-Ferrous China Selatan SMM (ke-3) 2026.
Kailida menantikan pertemuan dengan Anda di Konferensi Tahunan Logam Non-Ferrous China Selatan SMM (ke-3) 2026.
12 jam yang lalu
Rasio waran yang dibatalkan LME meningkat secara signifikan.
13 jam yang lalu
Rasio waran yang dibatalkan LME meningkat secara signifikan.
Baca Selengkapnya
Rasio waran yang dibatalkan LME meningkat secara signifikan.
Rasio waran yang dibatalkan LME meningkat secara signifikan.
Berdasarkan data persediaan LME terbaru, pada 21 Agustus, total persediaan tembaga LME mencapai 240.250 ton metrik; waran terdaftar sebanyak 118.875 ton metrik, turun 29,49% dari hari perdagangan sebelumnya; waran yang dibatalkan sebanyak 121.375 ton metrik, meningkat 73,45% dari hari perdagangan sebelumnya; rasio pembatalan melonjak 21,19 poin persentase menjadi 50,52%.
13 jam yang lalu
The Kakula copper project is ahead of schedule and is expected to be put into production in the third quarter of 2021. - Shanghai Metals Market (SMM)