Norwegian Arctic Copper Project-critics are considering whether legal action could be delayed

Telah Terbit: Feb 18, 2019 10:03

SMM2, 18 Feb: Norway has approved the Arctic Copper Project, which has been described as "the most environmentally destructive project in Norwegian history"

Local Sami herders and fishermen argue that the plan will exacerbate existing problems affecting their homes and livelihoods, such as climate change, oil spills and poaching. Oslo, Norway, approved the plan on Thursday.

As many as 66 million tons of copper are believed to be buried underground in Kvalsund, Finnmark. Finmark is the northernmost part of the European Arctic Circle.

Environmentalists worry that this will lead to mining and drilling projects in other vulnerable ecosystems in the Arctic. The Arctic has become the latest frontier in the rapid depletion of mineral and fossil fuel reserves.

Melting sea ice has allowed heavily polluted ships to enter their original habitats, and countries are coveting their precious natural resources.

The Arctic is warming twice as fast as the rest of the planet, and current trends suggest that the Arctic will be ice-free as early as the summer of the 1950s.

This opens up business opportunities for resource extraction and cruise ships.

Nussir, the Norwegian mining company with full mining rights, said it would take advantage of the region's deep-sea ice-free ports, a major road and a "developing industrial zone" that has been built. The company says it is committed to minimizing interference with the way of life in its communities.

Norwegian Industry Minister Tobijoen Roy Isaksen (Torbjoern Roe Isaksen) also insisted that the project would make a positive contribution to local communities by providing new jobs and skills.

But Nils Mathis Sara, a reindeer herder, says the plan proves that Oslo is not taking their concerns seriously. He was shocked by the Government's decision and hoped that the Norwegian Government would hear their arguments.

Environmental groups worry that mining copper will destroy the land on which reindeer live in the summer.

A plan to dump mining waste into the coastline of Lipa Fjord threatens the spawning grounds of Atlantic salmon.

Silje Ask Lundberg, head of Friends of the Earth, said it was one of the most environmentally damaging industrial projects in Norwegian history. This decision makes it clear that governments do not take the struggle to protect marine life seriously and prefer to put short-term interests above conservation and sustainable development.

Activists say 2 million tons of heavy metal waste will be dumped into a fjord each year, the equivalent of 17 trucks an hour.

Earlier, mine waste dumped in the same fjord was lower than planned in the project approved today, resulting in a significant decline in salmon populations, which took 13 years to recover. Cod stocks have still not returned to their former spawning grounds.

Norway is the only country in Europe that allows mining companies to dump solid mine waste directly into the sea and is one of only five countries in the world to allow this.

Earthworks, an environmental charity, said the dumping of mine waste in the Rippa fjord in the 1970s "almost destroyed" the region's fisheries.

Critics are considering whether to take legal action, which could delay the project. The project has been awaiting government approval since it was approved by local officials in 2012.

About 2500 people took part in civil disobedience activities against the project.

The British government has been promoting mining in the Arctic, writing in 2014 that Norway's "rich mineral resources" offer "excellent growth opportunities".

Norwegian government approves the plan to mine copper deposits in the Arctic Circle

(note: if copyright issues are involved, please contact SMM and we will deal with "View the original text" in a timely manner)

Scan QR code, apply to join SMM metal exchange group, please indicate company + name + main business

Pernyataan Sumber Data: Kecuali informasi yang tersedia untuk publik, semua data lainnya diproses oleh SMM berdasarkan informasi publik, komunikasi pasar, dan mengandalkan model database internal SMM. Hanya untuk referensi dan tidak menjadi rekomendasi pengambilan keputusan.

Untuk pertanyaan atau informasi lebih lanjut, silakan hubungi: lemonzhao@smm.cn
Untuk informasi lebih lanjut tentang cara mengakses laporan penelitian kami, hubungi:service.en@smm.cn
Berita Terkait
Proyek Katoda Tembaga 300.000 mt Yingkou Jianfa Shenghai Tahap I Tungku Peleburan Mulai Berproduksi, Sistem Pirometalurgi Memasuki Tahap Pengeringan Tungku
2 jam yang lalu
Proyek Katoda Tembaga 300.000 mt Yingkou Jianfa Shenghai Tahap I Tungku Peleburan Mulai Berproduksi, Sistem Pirometalurgi Memasuki Tahap Pengeringan Tungku
Baca Selengkapnya
Proyek Katoda Tembaga 300.000 mt Yingkou Jianfa Shenghai Tahap I Tungku Peleburan Mulai Berproduksi, Sistem Pirometalurgi Memasuki Tahap Pengeringan Tungku
Proyek Katoda Tembaga 300.000 mt Yingkou Jianfa Shenghai Tahap I Tungku Peleburan Mulai Berproduksi, Sistem Pirometalurgi Memasuki Tahap Pengeringan Tungku
Pada 12 September pukul 9:58, tungku peleburan inti sistem pirometalurgi di proyek pemulihan multi-logam Yingkou Jianfa Shenghai Nonferrous Metals & Chemicals Co., Ltd. berhasil dinyalakan, secara resmi memasuki tahap pengeringan tungku dan menandai langkah kunci menuju commissioning dan produksi seluruh lini. Informasi publik menunjukkan bahwa proyek peningkatan teknologi pemulihan komprehensif bijih emas-perak polimetalik kompleks, relokasi, dan perluasan Yingkou Jianfa Shenghai menggunakan konsentrat tembaga sebagai bahan baku utama, dengan kapasitas terencana keseluruhan 600.000 ton/tahun katoda tembaga yang akan dibangun dalam dua fase, dengan kapasitas 300.000 ton/tahun per fase. Fase I dirancang untuk memproduksi 300.000 ton/tahun katoda tembaga dan 1,18 juta ton/tahun asam sulfat, beserta sistem pendukung untuk peleburan, konversi, pemurnian anoda, elektrolisis, benefisiasi terak, dan pemulihan logam mulia. Setelah penyalaan ini, proyek akan melaksanakan pengeringan tungku terstandarisasi dan uji coba terpadu kondisi panas di seluruh sistem untuk memverifikasi peralatan, instrumen, interlock, dan sistem kontrol otomatis. Proyek ini belum secara resmi memulai pengumpanan bahan baku dan produksi; setelah pengeringan tungku dan commissioning sistem selesai, akan dilanjutkan dengan commissioning kapasitas katoda tembaga 300.000 ton/tahun Fase I. Jika proyek berhasil mulai berproduksi, diharapkan dapat meningkatkan kapasitas peleburan tembaga di Tiongkok Utara dan semakin mendorong permintaan domestik akan bahan baku konsentrat tembaga.
2 jam yang lalu
Alchemy Resources Mulai Pengeboran Target Tembaga-Emas di Yellow Mountain
18 jam yang lalu
Alchemy Resources Mulai Pengeboran Target Tembaga-Emas di Yellow Mountain
Baca Selengkapnya
Alchemy Resources Mulai Pengeboran Target Tembaga-Emas di Yellow Mountain
Alchemy Resources Mulai Pengeboran Target Tembaga-Emas di Yellow Mountain
Alchemy Resources mengumumkan pada 11 September bahwa pengeboran sirkulasi balik telah dimulai di proyek Yellow Mountain dan Overflow di New South Wales, Australia, dengan hingga 15 lubang direncanakan selama kampanye eksplorasi terbaru. Di proyek Yellow Mountain yang 80% dimilikinya, pengeboran akan menguji perluasan mineralisasi tembaga-emas dan polimetalik yang telah diidentifikasi sebelumnya, serta dua target geofisika yang belum pernah dibor sebelumnya. Pengeboran sebelumnya di Yellow Mountain menghasilkan irisan sepanjang 113 meter dengan kadar setara tembaga 1,17%, terdiri dari 0,33% tembaga, 0,37 g/t emas, 24,3 g/t perak, 0,86% timbal, dan 1,23% seng. Kampanye pengeboran terbaru dirancang untuk menguji apakah sistem mineralisasi yang diketahui meluas ke area target yang baru diidentifikasi. Program ini juga akan mencakup pengeboran di proyek Overflow, di mana Alchemy menargetkan perluasan mineralisasi yang ada di sepanjang jurus dan di kedalaman. Overflow saat ini memiliki sumber daya mineral terindikasi sekitar 342.000 ons setara emas dan mengandung mineralisasi emas, perak, tembaga, timbal, dan seng. Dimulainya pengeboran memberikan uji jangka pendek terhadap skala dan kontinuitas mineralisasi di Yellow Mountain. Irisan tembaga-emas-polimetalik lebar yang dilaporkan sebelumnya menunjukkan potensi sistem mineralisasi yang cukup besar, sementara target geofisika yang baru ditetapkan memberikan potensi eksplorasi tambahan. Hasil pengeboran akan menjadi penting dalam menentukan apakah jejak mineralisasi dapat diperluas secara material.
18 jam yang lalu
CEO Freeport Sinyalkan Kemungkinan Lanjutkan Ekspansi Tembaga Bagdad Senilai $4,5 Miliar
18 jam yang lalu
CEO Freeport Sinyalkan Kemungkinan Lanjutkan Ekspansi Tembaga Bagdad Senilai $4,5 Miliar
Baca Selengkapnya
CEO Freeport Sinyalkan Kemungkinan Lanjutkan Ekspansi Tembaga Bagdad Senilai $4,5 Miliar
CEO Freeport Sinyalkan Kemungkinan Lanjutkan Ekspansi Tembaga Bagdad Senilai $4,5 Miliar
Chief Executive Officer Freeport-McMoRan Kathleen Quirk mengindikasikan bahwa perusahaan berharap dapat melanjutkan rencana perluasan tambang tembaga Bagdad di Arizona, menandakan komitmen yang lebih kuat terhadap proyek tersebut menjelang keputusan investasi formal. Berbicara di Jefferies Global Industrials Conference pada 10 September, Quirk mengatakan proyek tersebut masih memerlukan masukan dari dewan direksi Freeport, tetapi ia memperkirakan perusahaan akan melanjutkannya. Ia menggambarkan perluasan tersebut sebagai proyek konstruksi sekitar tiga tahun dan mencatat bahwa tidak ada hambatan perizinan besar yang diperkirakan. Estimasi proyek terbaru Freeport menempatkan belanja modal untuk perluasan Bagdad sekitar US$4,5 miliar, sekitar 30% di atas estimasi sebelumnya sebesar US$3,5 miliar, mencerminkan kenaikan biaya, perubahan lingkup, dan rekayasa tambahan. Proyek tersebut akan lebih dari dua kali lipat meningkatkan kapasitas konsentrator di Bagdad dan diperkirakan menambah sekitar 200–250 juta pon, atau sekitar 91.000–113.000 ton, produksi tembaga per tahun, bersama dengan tambahan 10–12 juta pon molibdenum. Bagdad saat ini memiliki umur cadangan lebih dari 80 tahun. Pengajuan regulasi Q2 2026 Freeport telah menggambarkan proyek tersebut sedang dipersiapkan untuk kemungkinan keputusan investasi pada paruh kedua 2026. Komentar terbaru ini dengan demikian merupakan sinyal yang lebih positif dari manajemen mengenai kemungkinan pengembangan, meskipun persetujuan dewan formal belum diumumkan. Keputusan untuk melanjutkan Bagdad akan menjadi salah satu investasi pertumbuhan tembaga jangka pendek Freeport yang paling signifikan di AS. Potensi penambahan lebih dari 90.000 ton tembaga per tahun akan meningkatkan output AS Freeport secara material, meskipun produksi pertama masih beberapa tahun lagi mengingat periode konstruksi yang diperkirakan. Perhatian kini akan beralih ke persetujuan dewan formal dan keputusan investasi akhir.
18 jam yang lalu