Qiya Group's 2.6m kW Wind Power Project Enters Turbine Hoisting Stage in Xinjiang

Publié: May 25, 2025 21:43

"When the wind speed is less than 3 meters per second, blade installation can commence..." In April, at the Laojunmiao North Wind Power Planning Area in Mulei Kazak Autonomous County, Xinjiang, the author learned from Xinjiang Qiya New Energy Co., Ltd. that the 2.6 million kW wind power project (Section A) of Qiya Group's 3 million kW energy storage integration project has reached a critical milestone—construction has officially entered the stage of wind turbine hoisting.

This marks the successful completion of the preliminary construction and pouring phases of Qiya Group's new energy project's wind power generation, officially entering the peak period of substantive construction, laying a solid foundation for the full grid connection and operation of 112 wind turbines in this section by the end of this year.

Déclaration sur la source des données : À l'exception des informations publiques, toutes les autres données sont traitées par SMM sur la base d'informations publiques, d'échanges avec le marché et en s'appuyant sur le modèle de base de données interne de SMM. Ils sont fournis à titre indicatif uniquement et ne constituent pas des recommandations décisionnelles.

Pour toute demande d'information ou pour en savoir plus, veuillez contacter : lemonzhao@smm.cn
Pour plus d'informations sur l'accès à nos rapports de recherche, veuillez contacter :service.en@smm.cn
"When the wind speed is less than 3 meters per second, blade installat - Shanghai Metals Market (SMM)