The Kakula copper project is ahead of schedule and is expected to be put into production in the third quarter of 2021.

Publié: Jul 7, 2020 14:29

SMM7: Canadian mining company Ivanhoe said on Monday that the underground development of its Kakula copper mine has exceeded expectations and has now completed 5.1km ahead of schedule, totaling more than 17km. The Kakula copper mine is expected to be put into production in the third quarter of 2021.

In June, the mining team completed an underground development of 1729 meters, 575m ahead of schedule for the month.

Ivanhoe also said that Kakula's 2000-ton ore conveyor system began operation in June, which will further increase the speed of underground development of the mine.

Underground development in the next few months will soon transition to high-grade mining areas.

The project is the first mine in a number of planned Kamoa-Kakula projects in the Democratic Republic of the Congo.

The Kamoa-Kakula copper project is a joint venture between Ivanhoe Mining (39.6%), Zijin Mining Group (39.6%), Crystal River Global Limited (0.8%) and the Government of the Democratic Republic of the Congo (20%).

The latest resource estimate for the large project, which was delivered in February, shows that it holds 1.4 billion tonnes of copper with a grade of 2.74 per cent (83.7 billion pounds) and another 339 million tonnes of inferred ore with a grade of 1.68 per cent and a copper content of 12.5 billion pounds (1 per cent).

"Click to participate in the second China (Yingtan) Copper Industry Summit Forum and the 15th China International Copper Industry chain Summit"

Scan the code to sign up for the summit or apply to join the SMM industry exchange group:

Déclaration sur la source des données : À l'exception des informations publiques, toutes les autres données sont traitées par SMM sur la base d'informations publiques, d'échanges avec le marché et en s'appuyant sur le modèle de base de données interne de SMM. Ils sont fournis à titre indicatif uniquement et ne constituent pas des recommandations décisionnelles.

Pour toute demande d'information ou pour en savoir plus, veuillez contacter : lemonzhao@smm.cn
Pour plus d'informations sur l'accès à nos rapports de recherche, veuillez contacter :service.en@smm.cn
Actualités Connexes
Foshan Huahong Copper Pipe & Tube, fabricant leader du Guangdong, annonce sa fermeture.
il y a 11 heures
Foshan Huahong Copper Pipe & Tube, fabricant leader du Guangdong, annonce sa fermeture.
Lire la suite
Foshan Huahong Copper Pipe & Tube, fabricant leader du Guangdong, annonce sa fermeture.
Foshan Huahong Copper Pipe & Tube, fabricant leader du Guangdong, annonce sa fermeture.
Le 21 août, la société Foshan Huahong Copper Pipe & Tube Co., Ltd., située dans le bourg de Shishan, district de Nanhai, ville de Foshan, a annoncé la cessation de ses activités. Fondée en 2004 avec un capital social de 150 millions de RMB, elle fut autrefois une entreprise leader dans l'industrie des tubes et tuyaux en cuivre pour la réfrigération à Foshan. Elle figurait également parmi les 500 premières entreprises manufacturières de la province du Guangdong et était reconnue comme une entreprise provinciale de haute technologie.
il y a 11 heures
Kailida se réjouit de vous rencontrer à la conférence annuelle 2026 SMM (3e) des métaux non ferreux de la Chine du Sud.
il y a 12 heures
Kailida se réjouit de vous rencontrer à la conférence annuelle 2026 SMM (3e) des métaux non ferreux de la Chine du Sud.
Lire la suite
Kailida se réjouit de vous rencontrer à la conférence annuelle 2026 SMM (3e) des métaux non ferreux de la Chine du Sud.
Kailida se réjouit de vous rencontrer à la conférence annuelle 2026 SMM (3e) des métaux non ferreux de la Chine du Sud.
il y a 12 heures
Le ratio des warrants annulés du LME a augmenté significativement.
il y a 13 heures
Le ratio des warrants annulés du LME a augmenté significativement.
Lire la suite
Le ratio des warrants annulés du LME a augmenté significativement.
Le ratio des warrants annulés du LME a augmenté significativement.
Selon les dernières données d'inventaire du LME, au 21 août, les stocks totaux de cuivre du LME s'élevaient à 240 250 tonnes ; les warrants enregistrés étaient de 118 875 tonnes, en baisse de 29,49% par rapport au jour de bourse précédent ; les warrants annulés étaient de 121 375 tonnes, en hausse de 73,45% par rapport au jour de bourse précédent ; le taux d'annulation a bondi de 21,19 points de pourcentage pour atteindre 50,52%.
il y a 13 heures
The Kakula copper project is ahead of schedule and is expected to be put into production in the third quarter of 2021. - Shanghai Metals Market (SMM)