[SMM Analysis] Rio Tinto Targets 200,000 tpy LCE Production by 2028

Published: Feb 28, 2026 15:49

This month, Rio Tinto stated during its earnings conference call that with all its owned projects progressing as planned, the company's lithium production capacity is expected to reach 200,000 metric tons of lithium carbonate equivalent (LCE) annually by 2028. The increase will primarily stem from the Fenix project, the expansion of Sal de Vida, and the commissioning of the Rincon and Nemaska projects. By that time, total output will exceed three times the 57,000 metric tons of lithium carbonate production achieved in 2025.

Rio Tinto previously announced its entry into the ranks of major lithium producers upon acquiring Arcadium, with plans to increase capacity to over 200,000 metric tons of lithium carbonate equivalent (LCE) annually by 2028. The company has now confirmed its focus on achieving this target, positioning lithium as a “significant” component within its business structure.

Expansion Projects:

The mechanical portion of the 10,000-ton-per-year expansion at Fenix, one of the Argentine salt lake projects, has been completed, with commissioning progress reaching 60%. The mechanical vapor recompression unit has been put into operation to support the planned first production run. The first production from the expanded capacity remains on track to commence in the second half of 2026.

At the new Sal de Vida project in Argentina, with an annual capacity of 15,000 metric tons, the mechanical works have been completed and commissioning is 40% complete. Production is expected to commence in the second half of 2026, projected to increase Rio Tinto's lithium output to 61,000–64,000 metric tons LCE in 2026.

Regarding future projects:

The Rincon project in Argentina, with an annual capacity of 60,000 metric tons, is progressing smoothly with its initial 3,000-metric-ton-per-year plant. It is expected to reach full capacity by year-end. The 57,000-metric-ton expansion plant has completed commissioning and is currently being started up, with first production planned for 2028. It will reach full production after a three-year ramp-up period. The mine has an estimated 40-year lifespan, with operating costs positioned in the top quartile of the industry cost curve.

The Nemaska project in Canada features an integrated lithium hydroxide production line with a designed capacity of 28,000 metric tons per year. The mine's engineering design is complete, with construction progress at 60%. The lithium hydroxide refinery is scheduled to commence commissioning in 2026 and achieve first production in 2028. For the Whabouchi and Galaxy mines, strategic business and capital discipline reviews are underway with Canadian partners to determine the development of one of these mines. A decision is expected in the first half of 2026 to secure an integrated spodumene supply solution for the lithium hydroxide plant by 2028.

In Chile, Rio Tinto anticipates closing agreements signed with state-owned mining companies Codelco and Enami in the first half of 2026. Rio Tinto has been selected as the private partner to develop Chile's two largest undeveloped lithium resources, with projects advancing upon agreement completion.

 

 

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM‘s internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or to learn more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
India to build a six-month strategic stockpile of lithium, cobalt and rare earths as demand rises
May 1, 2026 07:00
India to build a six-month strategic stockpile of lithium, cobalt and rare earths as demand rises
Read More
India to build a six-month strategic stockpile of lithium, cobalt and rare earths as demand rises
India to build a six-month strategic stockpile of lithium, cobalt and rare earths as demand rises
Amid sustained demand growth, India plans to build a strategic reserve of critical minerals including lithium, cobalt, nickel, copper and rare earths. The stockpile will be sized to cover six months of domestic consumption, aiming to guard against risks of global supply disruptions and sharp raw material price volatility. Led by India’s Ministry of Mines and Ministry of Heavy Industries, the reserve covers key raw materials essential for new energy vehicles, energy storage and the electronics sector, fields where India currently relies heavily on imports. At present, the United States, China, South Korea and other countries have already established strategic reserve systems for critical minerals.
May 1, 2026 07:00
[Geely's Gan Jiayue: Zeekr 9X to enter markets in the Middle East, Central Asia, and Europe from Q3]
Apr 30, 2026 23:00
[Geely's Gan Jiayue: Zeekr 9X to enter markets in the Middle East, Central Asia, and Europe from Q3]
Read More
[Geely's Gan Jiayue: Zeekr 9X to enter markets in the Middle East, Central Asia, and Europe from Q3]
[Geely's Gan Jiayue: Zeekr 9X to enter markets in the Middle East, Central Asia, and Europe from Q3]
On April 29, during Geely's Q1 2026 results conference, Gan Jiayue, CEO of Geely Auto Group, stated that the Zeekr 9X will be exported to the Middle East in June, launched in Central Asia in Q3, and enter the European market in Q4. Gan also revealed that the Zeekr 8X will be promoted in overseas markets from Q4 this year to Q1 next year. Data shows that in the first quarter, deliveries of the Zeekr 9X reached 22,000 units.
Apr 30, 2026 23:00
[LG Energy Solution posts Q1 operating loss of 207.8 billion won]
Apr 30, 2026 22:55
[LG Energy Solution posts Q1 operating loss of 207.8 billion won]
Read More
[LG Energy Solution posts Q1 operating loss of 207.8 billion won]
[LG Energy Solution posts Q1 operating loss of 207.8 billion won]
LG Energy Solution reported consolidated revenue of 6.6 trillion won in the first quarter, up 1.2% quarter-on-quarter (including approximately 189.8 billion won in North American production incentives). During the same period, it recorded an operating loss of 207.8 billion won. Shipments of pouch-type electric vehicle (EV) batteries declined due to inventory adjustments by major North American customers.
Apr 30, 2026 22:55
[SMM Analysis] Rio Tinto Targets 200,000 tpy LCE Production by 2028 - Shanghai Metals Market (SMM)