Qiya Group's 2.6m kW Wind Power Project Enters Turbine Hoisting Stage in Xinjiang

Publicado: May 25, 2025 21:43

"When the wind speed is less than 3 meters per second, blade installation can commence..." In April, at the Laojunmiao North Wind Power Planning Area in Mulei Kazak Autonomous County, Xinjiang, the author learned from Xinjiang Qiya New Energy Co., Ltd. that the 2.6 million kW wind power project (Section A) of Qiya Group's 3 million kW energy storage integration project has reached a critical milestone—construction has officially entered the stage of wind turbine hoisting.

This marks the successful completion of the preliminary construction and pouring phases of Qiya Group's new energy project's wind power generation, officially entering the peak period of substantive construction, laying a solid foundation for the full grid connection and operation of 112 wind turbines in this section by the end of this year.

Declaración de Fuente de Datos: Excepto la información disponible públicamente, todos los demás datos son procesados por SMM basándose en información pública, comunicación de mercado y confiando en el modelo de base de datos interna de SMM. Son solo para referencia y no constituyen recomendaciones para la toma de decisiones.

Para cualquier consulta o para obtener más información, por favor contacte: lemonzhao@smm.cn
Para más información sobre cómo acceder a nuestros informes de investigación, contacte con:service.en@smm.cn