Hudbay Minerals Obtains All Permits for the Copper World Project in Arizona

Publicado: Jan 3, 2025 15:46
[Hudbay Minerals Secures All Permits for Arizona Copper World Project] According to external sources on January 2, Hudbay Minerals' proposed Copper World project in Arizona, with an annual capacity of 85,000 mt, has now fully obtained development permits after receiving all three critical state-level permits. The mining company announced on Thursday that the Arizona Department of Environmental Quality (ADEQ) has issued the air quality permit. The company stated that, along with the previously granted aquifer protection and land reclamation approvals, the project has completed the permitting process. (Webstock Inc.)

According to Webstock Inc., citing foreign media on January 2, Hudbay Minerals' Copper World project in Arizona, with an annual capacity of 85,000 mt, has now fully obtained development permits after securing all three key state-level approvals.

On Thursday, the mining company announced that the Arizona Department of Environmental Quality (ADEQ) had issued an air quality permit. The company stated that, along with previous approvals for aquifer protection and land reclamation, the project has completed the permitting process.

Peter Kukielski, the company's CEO, said in a press release: "With the Copper World project receiving the air quality permit, we firmly believe Hudbay now possesses one of the best copper development projects in the Americas."

Securing state-level permits means Hudbay has completed the first part of the Copper World project's 3-P (three prerequisites) plan.

The company now shifts its focus to the second prerequisite, which is completing the Definitive Feasibility Study (DFS) with an internal rate of return exceeding 15%. Feasibility-related studies have already commenced, targeting completion in H1 2026.

The third prerequisite involves a multifaceted financing strategy, including a committed minority joint venture partner. This process is expected to begin in early 2025. Any participating partner is anticipated to contribute to funding the DFS activities in 2025, as well as the final design and construction of the Copper World project.

According to Hudbay, the Copper World project is expected to increase consolidated annual copper production by more than 50% from current levels, with an initial mine life of 20 years. The project's operations will serve as a critical contributor to the domestic supply chain in the US.

Based on the latest pre-feasibility study for Phase 1 of the Copper World project, the project's post-tax net present value is $1.1 billion (at an 8% discount rate), with an internal rate of return of 19%, calculated at a copper price of $3.75 per pound.

Declaración de Fuente de Datos: Excepto la información disponible públicamente, todos los demás datos son procesados por SMM basándose en información pública, comunicación de mercado y confiando en el modelo de base de datos interna de SMM. Son solo para referencia y no constituyen recomendaciones para la toma de decisiones.

Para cualquier consulta o para obtener más información, por favor contacte: lemonzhao@smm.cn
Para más información sobre cómo acceder a nuestros informes de investigación, contacte con:service.en@smm.cn
Noticias relacionadas
High copper prices suppress downstream purchasing, with operating rates and new orders continuing to decline
hace 1 minuto
High copper prices suppress downstream purchasing, with operating rates and new orders continuing to decline
Leer más
High copper prices suppress downstream purchasing, with operating rates and new orders continuing to decline
High copper prices suppress downstream purchasing, with operating rates and new orders continuing to decline
High copper prices and weak demand exerted dual pressure, keeping the enamelled wire industry in a subdued trend. This week, the operating rate of enamelled wire industry machines fell 2.47 percentage points WoW, and new order intake dropped 1.14 percentage points WoW.
hace 1 minuto
Altos precios del cobre frenan las compras de los transformadores; la tasa de operación y los nuevos pedidos siguen cayendo [Reseña semanal del mercado de alambre esmaltado de SMM]
hace 5 minutos
Altos precios del cobre frenan las compras de los transformadores; la tasa de operación y los nuevos pedidos siguen cayendo [Reseña semanal del mercado de alambre esmaltado de SMM]
Leer más
Altos precios del cobre frenan las compras de los transformadores; la tasa de operación y los nuevos pedidos siguen cayendo [Reseña semanal del mercado de alambre esmaltado de SMM]
Altos precios del cobre frenan las compras de los transformadores; la tasa de operación y los nuevos pedidos siguen cayendo [Reseña semanal del mercado de alambre esmaltado de SMM]
La tasa de operación de las máquinas de la industria de alambre esmaltado cayó esta semana en comparación con la semana anterior (21 de agosto - 27 de agosto) ....
hace 5 minutos
Capstone completa la adquisición de San Pietro y consolida el distrito cuprífero de Atacama
hace 14 minutos
Capstone completa la adquisición de San Pietro y consolida el distrito cuprífero de Atacama
Leer más
Capstone completa la adquisición de San Pietro y consolida el distrito cuprífero de Atacama
Capstone completa la adquisición de San Pietro y consolida el distrito cuprífero de Atacama
Capstone Copper completó la adquisición del proyecto de cobre-oro-hierro-cobalto San Pietro en la región de Atacama, Chile, el 31 de agosto de 2026, pagando 25 millones de dólares en acciones de Capstone a New Golden Exploration Chile, una empresa conjunta de Golden Arrow y SSA. Situado entre sus propiedades Mantoverde, Santo Domingo y Sierra Norte, San Pietro añade unas 16.000 hectáreas de terreno de alto potencial. Los depósitos Rincones y Colla albergan un recurso inferido de 492 millones de toneladas con 0,23% de cobre y 0,05 g/t de oro. En un radio de 20 km, las concesiones de Capstone contienen ahora aproximadamente 1.600 millones de toneladas de recursos medidos e indicados, más 1.400 millones de toneladas inferidos. Tras la compra de Sierra Norte en 2024 y una opción con ENAMI en 2025, el acuerdo consolida la infraestructura del distrito y amplía las opciones de crecimiento futuro en cobre.
hace 14 minutos