On 26 June, E3 Lithium announced the pre-feasibility study for its Clearwater Project located in Alberta, Canada. The project will require an estimated US$2.5 billion to build 32,250 tons of lithium hydroxide monohydrate (LHM) production capacity.
Initial operating costs are estimated at US$6,200 per ton of LHM, and average operating cost is at US$7,250 per ton, with the LHM price estimated at US$31,344 per ton.
E3 plans to utilize 38 wellpads in the Leduc oil reservoir to extract lithium brine. The project highlights the employment of a direct lithium extraction process using an aluminate-based sorbent, coupled with recycled water and carbon sequestration to minimize emissions. A natural gas plant will power the operation.
Compared with previous disclosure, the study shows a significant improvement from a 2020 preliminary economic assessment, which had an after-tax net present value of US$820 million.
Author: Hongqiu Su | Battery Metals Analyst Associate | London Office, Shanghai Metals Market
Email: lilysu@smm.cn
![El soporte de costos se debilita, la resiliencia de la demanda persiste; los precios del coque, materia prima para ánodos, en un estancamiento a corto plazo [Revisión semanal del mercado de materias primas para ánodos de baterías de litio de SMM]](https://imgqn.smm.cn/usercenter/QXufg20251217171730.jpg)
![Persiste el equilibrio ajustado entre oferta y demanda, con un impulso alcista gestándose en medio de precios estancados [Revisión semanal del mercado de materias primas para ánodos de baterías de litio de SMM]](https://imgqn.smm.cn/usercenter/oVqJl20251217171730.jpg)