[SMM PV Flash] Japan's Ground-Mounted Solar FIT/FIP Certification Enters Final Window, Deadline December 11
Japan's Agency for Natural Resources and Energy has set December 11 as the deadline for new and amended FIT/FIP certification applications for solar of 10 kW and above, wind, hydro and geothermal in fiscal 2026 — the final year ground-mounted commercial solar can be certified before the category is excluded from FIT and FIP from fiscal 2027 (from April 1). Applications must include grid-connection agreement documents, and projects without a connection agreement by the deadline cannot be certified this fiscal year, while projects subject to environmental assessment may submit scoping proof by January 29, 2027. The deadline for solar below 10 kW is January 5, 2027, and the Japan Photovoltaic Energy Association, which published the notice on November 9, expects above-normal application volumes. The government has proposed keeping priority support for four non-rooftop categories, including solar on government-owned land and solar carports, from April 1, 2027.