[Algoma Steel resolves power issues, prepares to start second EAF in Q4]
Algoma Steel said its August power outage problems are resolved as it prepares to start up a second electric arc furnace (EAF) in Q4. Third-quarter shipments are seen at about 131,500 tonnes, down from 164,600 tonnes in Q2, with a projected loss of 10-20 million USD, narrowing from the 96 million USD Q2 loss that came with a record 113,400 tonnes of plate. Trump tariffs have driven Algoma to shift its customer base from the US to Canadian shipbuilding, defence, major projects and energy extraction. CEO Rajat Marwah said a replacement turbine at Lake Superior Power is installed and all electrical equipment on EAF Unit Two has been tested, with first heat expected within days. The first EAF started earlier this year.