Latrobe Magnesium Shifts Strategy to Prioritize 50,000 mt Magnesium Smelting Project in South Carolina, US [SMM Survey]

Published: Sep 17, 2026 09:15
[SMM Magnesium Survey: Latrobe Magnesium Shifts Strategy to Prioritize 50,000 mt Magnesium Smelting Project in South Carolina, US] Australia's Latrobe Magnesium (ASX:LMG) has announced its latest plan to build a new primary magnesium plant with an annual capacity of 50,000 mt in South Carolina, US, with a long-term expansion potential to 100,000 mt/year, while its commercial project in Australia has been postponed. The project has secured a site and a long-term raw material supply agreement for nickel-iron slag, obtained letters of intent for 32,000 mt/year of offtake, and is supported by matching subsidies and tax incentives from South Carolina, with the company currently in financing negotiations. North America currently has no commercial primary magnesium capacity, and magnesium is included on the US critical minerals list, so the project aims to fill the gap in North America's magnesium supply chain.

Australian publicly listed firm Latrobe Magnesium announced a strategic adjustment on September 15, prioritizing its magnesium smelting project in South Carolina while deferring its large-scale magnesium project in Victoria until the regulatory framework for mine legacy issues is in place. Phase 1 has a designed capacity of 50,000 mt/year, with downstream letters of intent totaling 32,000 mt/year secured, accounting for 64% of Phase 1 capacity, alongside substantial potential demand from North America and globally. Raw material supply is underpinned by a 20-year binding memorandum with Société Le Nickel, ensuring ample nickel-iron slag feedstock reserves to support long-term operations. Total capital expenditure is estimated at $1.1-1.5 billion, with financial projections indicating sound returns, excluding local policy incentives. The company plans to commence feasibility studies in Q1 2027, complete FID in March 2028, with a 24-month construction period and production startup in April 2030. Pre-feasibility work, land acquisition, and establishment of a US subsidiary require $30 million in financing.

The company's Stage 1B magnesium demonstration plant in Australia's Latrobe Valley is 70% complete, with core equipment in place and commissioning underway, targeting first magnesium metal production in H2 2026. The plant employs a process to extract magnesium from lignite fly ash solid waste, with magnesium oxide technology validation already completed. US distributor Metal Exchange LLC has paid a $2 million prepayment, with all demonstration plant output designated for the US market. Full process validation at the demonstration plant will confirm the feasibility of the company's technology, providing technical support for the large-scale commercial project in South Carolina. North America currently has no primary magnesium capacity, global primary magnesium supply is highly concentrated, and Australian-produced magnesium can circumvent US tariff barriers. The enterprise plans to leverage its proprietary technology to fill the gap in US domestic magnesium supply.

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM's internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or for more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
Producers' willingness to hold prices firm rises, magnesium ingot maintains consolidation [SMM magnesium ingot spot express]
15 hours ago
Producers' willingness to hold prices firm rises, magnesium ingot maintains consolidation [SMM magnesium ingot spot express]
Read More
Producers' willingness to hold prices firm rises, magnesium ingot maintains consolidation [SMM magnesium ingot spot express]
Producers' willingness to hold prices firm rises, magnesium ingot maintains consolidation [SMM magnesium ingot spot express]
[Producers' willingness to hold prices firm rises, magnesium ingot maintains consolidation] The magnesium ingot market consolidated today. Producers chose to hold prices firm, boosted by yesterday's transactions, but downstream purchasing follow-through was weak. Foreign trade orders have not shown sustained recovery, and both domestic and external demand lack growth. The short-term market is expected to remain in consolidation.
15 hours ago
Anhui Baomai Establishes National Postdoctoral Research Station for Magnesium Innovation
16 hours ago
Anhui Baomai Establishes National Postdoctoral Research Station for Magnesium Innovation
Read More
Anhui Baomai Establishes National Postdoctoral Research Station for Magnesium Innovation
Anhui Baomai Establishes National Postdoctoral Research Station for Magnesium Innovation
【SMM Magnesium Flash】Recently, Anhui Baomai Light Alloy Co., Ltd., a subsidiary of Baowu Magnesium Industry, has been approved to establish a national-level postdoctoral research station. Anhui Baomai has led the establishment of the province's only magnesium-based new material industry innovation research institute, with a total of 38 patents applied. Its base has a total investment of over ten billion yuan, achieving integrated operation from mining to smelting to deep processing through a 23-kilometer raw material corridor. The research station will focus on tackling core technologies such as lightweighting for new energy vehicles and magnesium hydrogen storage. With the implementation of this platform, the cultivation of high-level talent and the transformation of research achievements in magnesium-based new materials are expected to accelerate further, helping Chizhou build a world-class production base for magnesium-based new materials.
16 hours ago
Australian Latrobe Magnesium Shifts Focus to US $1.5B Magnesium Project in South Carolina
16 hours ago
Australian Latrobe Magnesium Shifts Focus to US $1.5B Magnesium Project in South Carolina
Read More
Australian Latrobe Magnesium Shifts Focus to US $1.5B Magnesium Project in South Carolina
Australian Latrobe Magnesium Shifts Focus to US $1.5B Magnesium Project in South Carolina
【SMM Magnesium Flash】On September 15th, Latrobe Magnesium of Australia announced a strategic shift, prioritizing the advancement of a project with an annual production capacity of 50,000 tons of primary magnesium metal in South Carolina, USA. The company has secured a total of 32,000 tons/year of intended demand letters and has identified a site with supporting port logistics. The project utilizes nickel-iron slag as raw material and has signed a 20-year memorandum of understanding with Société Le Nickel, ensuring raw material supply for approximately 60 years of operation. The estimated capital expenditure for the project is between $1.1 billion and $1.5 billion. It is planned to initiate a feasibility study in the first quarter of 2027 and commence production in April 2030. This move is expected to fill the supply gap of primary magnesium in North America and contribute to the self-sufficiency of key minerals in the United States.