1. Procurement Conditions
This procurement project is for cable procurement of the New No.5 High-temperature Electric Furnace Power Supply System Project of the Forging Plant of Hevvy Machinery Design Institute (AGGZZBHGXHD260821312804). The purchaser is Ansteel Group Engineering Technology Development Co., Ltd., and the funds come from self-raised sources. The project has met the procurement conditions, and a public inquiry and comparison is now conducted.
2. Project Overview and Procurement Scope
2.1 Project name: Cable procurement for the New No.5 High-temperature Electric Furnace Power Supply System Project of the Forging Plant of Heavy Machinery Design Institute
2.2 Procurement failure transfer to other procurement method: No transfer
2.3 The procurement content, scope, and scale of this project are detailed in the attachment "Material List Attachment.pdf".
3. Bidder Qualification Requirements
3.1 This procurement does not allow consortium bidding.
3.2 This procurement requires bidders to have the following qualifications:
(1) Production-type business license
3.3 This procurement requires bidders to meet the following registered capital requirements:
Production-type registered capital: 5 million yuan or above
3.4 This procurement requires bidders to have the following performance requirements:
Provide one copy of supply performance (contract and corresponding invoice) similar to this tender project from January 1, 2022 to the present.
3.5 This procurement requires bidders to have the following capabilty, financial, and other requirements:
Financial requirements: See attachment (if needed)
Capabilty requirements: See attachment (if needed)
Other requirements: See attachment (if needed)
3.6 For projects that must undergo tender according to law, bidders subject to enforcement for dishonesty are invalid.
4. Acquisition of Procurement Documents
4.1 All interested bidders should log in to the Ansteel Smart Tender and Bid Platform at http://bid.ansteel.cn from 13:00 on August 24, 2026 to 08:00 on September 4, 2026 (Beijing time, the same hereinafter) to download electronic procurement documents.
Click to view tender details:

![[SMM Sheets & Plates Daily Comment] HRC futures surged alongside costs, with production still expected to edge down](https://imgqn.smm.cn/usercenter/ntiFA20251217171719.jpg)
![Tangshan Qian'an Raises Steel Billet Price by 10 to 3,000 Yuan/mt on August 24 [SMM Steel]](https://imgqn.smm.cn/usercenter/zLhJl20251217171720.jpg)