Energy Storage Tenders Frequently "Brake" as Industry Chain Prices Rise Across the Board
Recently, the EPC general contracting for the 100MW/200MWh standalone ESS power station project in Xigang Town, Tengzhou City, Shandong Province, issued a termination notice, just one day after the tender announcement was released. The reason for termination was "significant changes."
Also in July, the EPC for the 200MW/800MWh standalone ESS project in Usu City, Xinjiang, once again issued a tender termination notice, citing "significant adjustments to the construction content." This was already the third termination of the project's tender process.
Looking back at the tender history of the Usu project, its first tender was in November 2025, with a budget of 730 million yuan, equating to a unit price of 0.91 Yuan/Wh. It was later terminated due to significant changes in the technical specifications. After resumption, the budget was raised to approximately 807 million yuan, with the unit price rising to 1.01 Yuan/Wh. In January 2026, the project announced the winning bid result, with PowerChina Jiangxi Electric Power winning the bid at a unit price of 0.94 Yuan/Wh.