Tianli Lithium Energy's 1,500-2,000 Ton Lithium Iron Phosphate Production Line Resumes Operations Ahead Of Schedule
Tianli Lithium Energy issued an announcement on February 26, stating that its wholly-owned subsidiary, Sichuan Tianli Lithium Energy Co., Ltd., has completed the scheduled production line maintenance plan and fully resumed production operations on February 24, ahead of the originally planned date of February 28. It is understood that the production suspension for maintenance at Sichuan Tianli began on January 14, 2026, with the core objective of ensuring the efficient, stable, and safe operation of the lithium iron phosphate production line, thereby guaranteeing the smooth progress of subsequent safe production. During the maintenance period, Sichuan Tianli conducted a comprehensive inspection and upkeep of the production line, simultaneously carrying out upgrades and renovations.