BYD and others were shortlisted for the procurement tender of the 100MW/200MWh centralized shared ESS power station project of China Resources in Fangchenggang, Guangxi.

Published: Apr 27, 2025 13:23

Polaris Energy Storage Network learned that on April 26, the list of winning candidates for the energy storage system equipment procurement of the China Resources Power Fangchenggang Fangcheng District 100MW (200MWh) centralized shared ESS power station project was announced.

The first winning candidate was BYD Auto Industry Co., Ltd., with a bid price of 103.779 million yuan, equivalent to a unit price of 0.519 yuan/Wh.

The second winning candidate was CRRC Zhuzhou Electric Locomotive Research Institute Co., Ltd., with a bid price of 101.6 million yuan, equivalent to a unit price of 0.508 yuan/Wh.

The bid inviter was China Resources New Energy Investment Co., Ltd. Guangxi Branch. The project is located in Fangchenggang, Guangxi. The total capacity of the entire energy storage system is 100MW/200MWh. The supply of required equipment and related technical services includes but is not limited to ESS batteries, ESS equipment prefabricated cabins, battery management systems (BMS), PCS, energy storage monitoring systems, step-up transformers and their internal accessories (including fire protection and other auxiliary systems and equipment), etc. It is responsible for the installation and wiring of components such as PCS, step-up transformers, and battery prefabricated cabins that are self-supplied within the cabin. It is responsible for providing internal design documents of the energy storage system, including but not limited to the layout diagrams of various equipment in the energy storage system, electrical connection diagrams, communication system diagrams, and other related drawings within the supply scope, and the parameters of the energy storage system equipment. It is responsible for the installation guidance, training and technical services, commissioning, and after-sales services of the ESS batteries, ESS equipment prefabricated cabins, battery management systems (BMS), PCS, energy storage monitoring systems, step-up transformers and their internal accessories (including fire protection and other auxiliary systems and equipment), etc., ensuring that all data of the energy storage system (including all battery cell-level data) can be fully accessed by the operation management center.

The list of winning candidates for the energy storage system equipment procurement of the China Resources Power Fangchenggang Fangcheng District 100MW (200MWh) centralized shared ESS power station project was announced.

Announcement No.: SZBHX202504260012.

The energy storage system equipment procurement for the China Resources Power Fangchenggang Fangcheng District 100MW (200MWh) centralized shared ESS power station project (section No.: S03111725SZ0001P1) has completed the evaluation process through public tender, and the results are announced as follows:

I. Basic Information of the Project.

Project Name: China Resources Power Fangchenggang Fangcheng District 100MW (200MWh) Centralized Shared ESS Power Station Project.

Section Name: Energy Storage System Equipment Procurement.

Section No.: S03111725SZ0001P1.

Bid Inviter: China Resources New Energy Investment Co., Ltd. Guangxi Branch.

Tender Agency: China Resources Shouzheng Tendering Co., Ltd.

II. Evaluation Results.

1. First Winning Candidate: BYD Auto Industry Co., Ltd.

1.1 Bid Price: 103,779,000.00 yuan.

1.2 Quality: Meets the requirements of the tender documents.

1.3 Construction/Delivery/Service Period: Meets the requirements of the tender documents.

1.4 Project Leader Information: Name: -- Certificate Name: -- Certificate No.: --.

1.5 Qualification: Meets the requirements of the tender documents.

1.6 Performance:

2. Second Winning Candidate: CRRC Zhuzhou Electric Locomotive Research Institute Co., Ltd.

2.1 Bid Price: 101,600,000.00 yuan.

2.2 Quality: Meets the requirements of the tender documents.

2.3 Construction/Delivery/Service Period: Meets the requirements of the tender documents.

2.4 Project Leader Information: Name: -- Certificate Name: -- Certificate No.: --.

2.5 Qualification: Meets the requirements of the tender documents.

2.6 Performance:

3. Third Winning Candidate: /

3.1 Bid Price: /

3.2 Quality: /

3.3 Construction/Delivery/Service Period: /

3.4 Project Leader Information: /

3.5 Qualification: /

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM‘s internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or to learn more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
Shaanxi Construction No.7 Group's Hybrid ESS Project in Yuncheng Enters Trial Operation
4 hours ago
Shaanxi Construction No.7 Group's Hybrid ESS Project in Yuncheng Enters Trial Operation
Read More
Shaanxi Construction No.7 Group's Hybrid ESS Project in Yuncheng Enters Trial Operation
Shaanxi Construction No.7 Group's Hybrid ESS Project in Yuncheng Enters Trial Operation
Recently, the official account of Shaanxi Construction No. 7 Construction Group announced that Phase I of the 200 MW/301.75 MWh hybrid frequency regulation ESS power station project in the Yuncheng Economic and Technological Development Zone, Shanxi, which it undertook, was successfully connected to the grid and officially entered the trial operation stage. The project mainly includes the construction of a 50 MW flywheel independent frequency regulation ESS, a 150 MW LFP electrochemical ESS, a 220 kV substation, and supporting facilities, adopting a hybrid model of “flywheel energy storage + LFP electrochemical energy storage.”
4 hours ago
Sinoma Overseas' PV+ESS Project in Xuzhou Officially Launches on March 16, 2026
4 hours ago
Sinoma Overseas' PV+ESS Project in Xuzhou Officially Launches on March 16, 2026
Read More
Sinoma Overseas' PV+ESS Project in Xuzhou Officially Launches on March 16, 2026
Sinoma Overseas' PV+ESS Project in Xuzhou Officially Launches on March 16, 2026
Recently, the PV+ESS integration project of Xuzhou Sinoma Cement Co., Ltd., invested in and built by Sinoma Overseas, successfully achieved a breakthrough at a key period and was officially energized and put into operation on March 16, 2026, marking the formal commissioning of this regional integrated demonstration project for “hybrid energy storage + PV.” The project deeply integrated PV power generation and hybrid energy storage technologies to establish a clean energy supply system featuring “self-generation for self-use, flexible regulation, safety, and high efficiency.” The project’s total ESS installations capacity reached 10 MW/20 MWh, with total PV capacity of 11.38 MW, forming a complete green energy chain of “PV power generation + hybrid energy storage,” providing continuous and stable power support for production processes, building a closed-loop smart energy system with deep integration across the power generation side, energy storage side, and power consumption side, and realizing intelligent coordination and optimized operation throughout the entire life cycle of energy production, storage, consumption, and regulation.
4 hours ago
Gaoyi County's 300 MW/600 MWh Shared ESS Power Station Achieves Full-Capacity Delivery
4 hours ago
Gaoyi County's 300 MW/600 MWh Shared ESS Power Station Achieves Full-Capacity Delivery
Read More
Gaoyi County's 300 MW/600 MWh Shared ESS Power Station Achieves Full-Capacity Delivery
Gaoyi County's 300 MW/600 MWh Shared ESS Power Station Achieves Full-Capacity Delivery
Recently, the Shijiazhuang Gaoyi County 300 MW/600 MWh shared ESS power station, a key new-type energy storage project in Hebei province, officially completed the full-capacity delivery of its ESS, marking this regional benchmark energy storage project’s entry into the critical stage before production and operation. The successful delivery of the Gaoyi County 300 MW/600 MWh shared ESS power station represents another landmark implementation of Zhiguang Energy Storage’s core technologies in large-scale shared energy storage projects in north China, further consolidating Zhiguang Energy Storage’s industry-leading position in the field of cascaded high-voltage, large-capacity energy storage.
4 hours ago