300 Million Yuan! Trial Production in June! A Guizhou Anode Material Project Updates Its Progress
According to the Dalong Development Zone News and Information Center, during the Labour Day holiday, construction sites of major key projects in Dalong Development Zone, Guizhou were bustling with activity and operating at full capacity.
At the project site of Guizhou Depu New Materials Technology Co., Ltd.'s 20,000 mt/year lithium-ion anode material project, nearly 60 workers remained at their posts, pushing forward with all construction tasks at full speed. "Currently, the main structures of two factory buildings have been completed. Workshop No. 3 is undergoing accelerated installation of 10 sets of roller mills, 45 sets of reactors, and other core equipment. Workshop No. 4 has completed the installation of roof panels and wall panels, and internal site leveling work is underway. The comprehensive building and the 110KV substation are also under simultaneous construction, with subsequent work to advance the improvement of fire protection facilities and hardening of the factory area roads," said Liu Shaofeng, the company's administrative supervisor. He noted that during the Labour Day holiday, workers strictly controlled project quality and safety, striving to achieve phased trial production by the end of June.