Chongqing Yidong 1000 kV Substation's 500 kV Project Passes Review, Set for 2028 Operation

Published: May 17, 2026 21:51
Recently, the feasibility study report of the 500 kV supporting project of the 1000 kV substation in Chongqing Yidong passed the review of the General Institute of Electric Power Planning and Design. The 500 kV supporting project of the Yudong 1000 kV substation will be included in the national power planning in July 2025, and is expected to start construction in 2027 and be put into operation in 2028.