Anhui Haili Casting Advanced Capacity Project Plans to Add Multiple Aluminum Die-Casting Lines
[SMM Express] According to reports, the Anhui Hanshan Haili Green Casting Advanced Capacity Project is being accelerated. The project covers a total land area of 79,000 m², with a building area of approximately 49,000 m². Plant No. 1 was completed in February and entered trial production. The main structure of Plant No. 2 is expected to be completed by month-end of May, with equipment installation set to begin in August. Upon completion, the project plans to add 1 cast iron line, 3 aluminum die-casting lines, and 1 compressor recycling and disassembly line to further expand capacity.