Ansteel Bayuquan to Start 26-Day Maintenance on 4,000m³ Blast Furnace, Impacting 9,000 mt Daily Production

Published: Feb 9, 2026 16:59
[Steel Mill Maintenance] Ansteel Bayuquan is expected to commence maintenance on a 4,000m³ blast furnace on February 25, with the maintenance period anticipated to last 26 days. The daily average hot metal production impact is estimated to be around 9,000 mt. [SMM Steel]