Shaanxi Construction No.7 Group's Hybrid ESS Project in Yuncheng Enters Trial Operation
Recently, the official account of Shaanxi Construction No. 7 Construction Group announced that Phase I of the 200 MW/301.75 MWh hybrid frequency regulation ESS power station project in the Yuncheng Economic and Technological Development Zone, Shanxi, which it undertook, was successfully connected to the grid and officially entered the trial operation stage. The project mainly includes the construction of a 50 MW flywheel independent frequency regulation ESS, a 150 MW LFP electrochemical ESS, a 220 kV substation, and supporting facilities, adopting a hybrid model of “flywheel energy storage + LFP electrochemical energy storage.”