CEEC Songyuan Hydrogen Park Exceeds 10,000 Tonnes Green Ammonia, Enters Large-Scale Commercial Phase

Published: Feb 6, 2026 18:01

Recently, good news has come from China Energy Construction (CEEC) Songyuan Hydrogen Industry Park (Integrated Green Hydrogen-Ammonia-Alcohol) Project — since its official commissioning on December 16, 2025, the cumulative output of green ammonia of the project has exceeded 10,000 tonnes. This milestone achievement marks that CEEC's hydrogen energy industry has successfully crossed the demonstration and exploration stage, entered a new era of large-scale commercial application, and provided a replicable and promotable practical model for the green and low-carbon industry.

As the "cornerstone project" for CEEC to deploy its hydrogen energy industry, the completion and commissioning of the Songyuan Project have effectively verified the green value of the "green electricity — green hydrogen — green ammonia/green alcohol" integrated commercial closed loop, and formed the independently innovative "Green Hydrogen No.1" solution. Immediately after commissioning, the project obtained the ISCC EU Green Certification and signed the world's first green ammonia ocean shipping fuel sales contract.

It is reported that the project is positioned as a pilot "three national-level demonstrations" for hydrogen energy projects in China's energy field and a global energy interconnection demonstration project, with China Energy Construction Co., Ltd. as the main project entity. The project content includes the following aspects:

New Energy Power Generation System: 800,000 kilowatts of new energy power generation (including 750,000 kilowatts of wind power and 50,000 kilowatts of photovoltaic power), adopting the green electricity direct supply mode.

Hydrogen Production and Chemical Equipment: An integrated production equipment with an annual output of 45,000 tonnes of green hydrogen and 200,000 tonnes of green ammonia/green methanol.

Supporting Facilities: Covering the entire industrial chain of hydrogen production, hydrogen storage, hydrogen-based chemicals, hydrogen energy equipment and technological R&D.

Technical Route: Integrated wind and photovoltaic direct supply + energy storage peak shaving + high-efficiency electrolytic hydrogen production system + dynamic ammonia synthesis.

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM‘s internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or to learn more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
Beijing Launches 500-kV Power Project in Fengtai, Boosting Grid Resilience and Industrial Growth
Feb 7, 2026 20:47
Beijing Launches 500-kV Power Project in Fengtai, Boosting Grid Resilience and Industrial Growth
Read More
Beijing Launches 500-kV Power Project in Fengtai, Boosting Grid Resilience and Industrial Growth
Beijing Launches 500-kV Power Project in Fengtai, Boosting Grid Resilience and Industrial Growth
On January 28th, the construction of the 500-kilovolt power transmission and transformation project in Fengtai, Beijing officially started. This project is the first newly-built 500-kilovolt power grid project in Beijing during the 15th Five-Year Plan period. It will significantly enhance the resilience and power receiving capacity of the southern Beijing power grid and provide reliable power support for Beijing to continuously optimize the investment structure and vigorously develop high-end, precise, and cutting-edge industries. The 500-kilovolt power transmission and transformation project in Fengtai, Beijing is a key project of Beijing's power grid during the 15th Five-Year Plan period and one of the "3 100" key projects in Beijing this year. It is constructed and managed by the State
Feb 7, 2026 20:47
Shaanxi-Anhui UHV DC Project's 500-kV AC System at Hezhou Station Begins Operation After Trial Run
Feb 7, 2026 20:44
Shaanxi-Anhui UHV DC Project's 500-kV AC System at Hezhou Station Begins Operation After Trial Run
Read More
Shaanxi-Anhui UHV DC Project's 500-kV AC System at Hezhou Station Begins Operation After Trial Run
Shaanxi-Anhui UHV DC Project's 500-kV AC System at Hezhou Station Begins Operation After Trial Run
On February 1st, the 500-kilovolt AC system of the Hezhou Converter Station, the receiving-end station of the ±800-kilovolt UHV DC power transmission project from northern Shaanxi to Anhui, was officially put into operation after a 24-hour trial run.
Feb 7, 2026 20:44
750-kV Power Line Connecting Northern to Central Shaanxi Fully Operational
Feb 7, 2026 20:44
750-kV Power Line Connecting Northern to Central Shaanxi Fully Operational
Read More
750-kV Power Line Connecting Northern to Central Shaanxi Fully Operational
750-kV Power Line Connecting Northern to Central Shaanxi Fully Operational
On February 2nd, the 750-kilovolt power transmission and transformation project of the third passageway from northern Shaanxi to central Shaanxi was fully connected. The project starts from the 750-kilovolt Shuofang Substation in Shenmu City in the north and ends at the 750-kilovolt Bailuyuan Substation in Lantian County in the south. It has newly built a 1,271-kilometer line, passing through 18 counties (districts) in 4 cities including Yulin, Yan'an, Weinan and Xi'an.
Feb 7, 2026 20:44